The Fryburg Rail Loading Facility located in Fryburg, North Dakota, was the construction of a 330 acre, 18 car rail loading facility for the Bakken Link Pipeline. The project included the installation of one mile of buried 10” pipeline that tied into two 155,000bbl storage tanks. From the storage tanks 18” pipelines ran to the pump house and from the pump house to the loading shed. Brahma was responsible for the design, procurement and construction of the structural steel pipe rack and the installation of the owner supplied rail loading pipe rack along with owner supplied specialties.

Brahma installed a series of foundations on this project including foundations for the tank car scale, thermal oxidizer, the pipe bridges, pipe supports, propane storage tanks and booster pump. Our scope of work included the installation and support of all piping and fittings both provided by the owner and procured by Brahma. We also installed the tank car loading rack, loading stations, stairs and associated equipment and structural steel. Our skilled craftsmen made accurate piping connections to the storage tanks, pumps, loading arms, thermal oxidizer, propane storage, and associated controls and instrumentation. Instrumentally we also installed the tank car scale controls.

The Bakken Link Pipeline spans 75 miles and ties into the Dry Creek & Three Forks pump stations along with the Watford City and Dunn Truck loading facilities.

Project Information

Client:
Great Northern Midstream
Location:
Fryburg, ND

Related Case Studies

Reid Gardner Security System Upgrade

The Reid Gardner Generating Station is a coal-fueled, steam-electric generating plant with four operating units. Three of the four units produce 100 megawatts, and the fourth unit produces 257 megawatts—collectively producing enough electricity to serve approximately 335,000 Nevada homes. Brahma was awarded the contract of upgrading the physical security system...

Tail Gas Unit

Tesoro is an independent refiner and marketer of petroleum products in the United States. The Salt Lake City Refinery began operations in 1908 and now operates as the largest refinery in Utah with a total crude-oil capacity of 58,000 barrels per day. The Tesoro Tail Gas Unit project was the...

Jeff Shockley

VP of Operations

Meet Jeff, an accomplished construction industry veteran and visionary leader with a robust 20-year trajectory of ascending from hands-on trade work to executive management. His leadership has been instrumental in steering multidisciplinary teams to success in diverse sectors such as Oil and Gas, Refining, Mining, Transportation, and Energy Transmission. Jeff’s mastery in Civil and Mechanical construction has been pivotal in the successful delivery of capital projects exceeding $1 billion in value. Jeff has essential experience in project controls and focuses on real-time tracking to provide the desired outcome to both the company and the client. His experience on both the Owner’s side as well as the contractor’s side has given him invaluable knowledge of management and the execution cycle.

Craig Rucker

VP of Operations

Meet Craig, a seasoned leader with over 26 years of management experience and technical expertise. His areas of specialization encompass a wide range of industry sectors, including project management, industrial facilities maintenance, plant maintenance, building and equipment structures, and construction management consultation.

Craig is certified in heavy rigging, with extensive experience in equipment removal and installation. His expertise extends to structural detailing, fabrication, erection, and installation. He also excels in conveyor system installation and maintenance, infrastructure improvements, capital project construction, bidding, estimating, and process piping and demolition.

Before joining Brahma, Craig honed his skills at Bell Steel, Inc. and Milling Machinery, Inc. His construction career, which began in the residential industry, eventually led him to industrial maintenance where he performed all aspects of millwright work. Craig’s commitment to continuous learning is evident in his completion of the ASU Alliance for Construction Excellence Project Management Course. He holds an OSHA 510 certification, a certification of completion in the Program of Project Management, and is trained in Auto CAD and Structural Steel detailing. With his vast experience and multitude of certifications, Craig brings a unique blend of leadership, technical acumen, and industry knowledge to his role.

Darren Patten

CEO

Meet Darren, a seasoned professional with an impressive track record spanning over 35 years in project management, engineering, and industrial facility management. His career is marked by proactive leadership in steering complex projects across various industries. His strategic approach to staffing, maintenance, and operations has consistently ensured optimal performance and cost-effectiveness.

Darren’s journey has taken him through notable companies such as NV Energy at the Reid Gardner Station, PacifiCorp- Huntington Plant, Abitibi Consolidated, and Geneva Steel Company. Each role has contributed to his rich tapestry of industry experience and technical expertise.

Known for his exceptional contract administration skills, Darren excels in resource management, delivering quality products at reasonable costs. His foresight allows him to identify potential problem areas early on and implement viable, cost-effective solutions. His commitment to meeting budgets and promoting safe, productive work environments is unwavering.

Darren holds a Bachelor of Science in Electrical Engineering, which forms the foundation of his technical acumen. Leveraging his top-tier education and extensive experience, Darren ensures that project teams adhere strictly to contract specifications. He vigilantly monitors contract performance, ensuring safe work practices, regulatory compliance, and adherence to budget and schedule constraints. Under Darren’s watchful eye, every project has been a testament to efficiency and quality, completed on time and within budget, with post-outage equipment performance exceeding expectations and installations meeting established technical standards.