Brahma performed the 4K02 Burner Upgrade for Ciner Wyoming in Green River, WY. Brahma’s pre-outage scope of work included mechanical and structural tasks
The structural scope of work included the installation of approximately 90,000 lbs. of structural steel, 2,000 sq. ft. of grating, 80 stair treads, 750 ft. of handrail, and other miscellaneous accoutermentS.
The mechanical scope of work included the installation of 200 ft. of 80 in. dia. ducting, 2,500HP ID Fan & Motor, 63’ tall Cyclone, 110K lb. drop-out chamber, 7 screw conveyors, 20’ x 9’ dia. 35K lb. burner, a combustion fan, an airlock, a new gas train and piping to interconnect all systems. Brahma also replaced the internal lifters of the 13’ 6” dia. x 70’ long 4K02 dryer. Brahma set a new MC building on new foundations.
Our post-outage scope of work included the installation of access platforms, stairs, handrails, and miscellaneous mechanical items.